Implementing new solutions
Commissioning, testing, training
One of the final stages of the investment implementation is the commissioning of the installation. Commissioning is carried out jointly by our designers and programmers.
Commissioning is divided into several stages:
- Electric start (directions of rotation, correct operation of sensors, valves and other field devices)
- I/O tests (checking input/output signals)
- Programming of programmable devices (inverters, sensors, specialized devices, calibration of measuring and weighing systems with appropriate calibration protocols)
- Filling in "drive cards" and "programmable device cards"
- Functional commissioning of production line sockets or machine parts
- Functional commissioning of the entire production line
- "Dry" tests - without the product
- "Wet" tests - with the product
The final stage of commissioning is the commissioning, together with the handover of the as-built documentation of the control system, including the operation and maintenance manual of the devices and components used. Commissioning is preceded by training in the field of operation, confirmed by appropriate protocols, and the provision of a complete operating manual for a given control system.
It often happens that after commissioning and commissioning, we provide an assistance service – our engineers stay on the premises to assist the staff in normal production activities